Market Data Advisory Notices
To Quote Vendors
From Market Data Operations
Subject FIX/FAST Conversion Timeline
Notice Date 2008-06-25
Notice Number Q2008-126
Effective Date 2008-06-25

As previously announced, the deadline for converting from the legacy RLC message format to FIX/FAST is October 17, 2008.  In an effort to better assist CME Group Quote Vendors during the conversion, we have outlined recommended key milestone dates in the table below. These will provide Quote Vendors with a baseline in tracking their progress during the FIX/FAST conversion. Please take a moment to carefully review the following dates. It is important to note that the first milestone is a week from tomorrow.

 

Recommended Key Milestones Dates

 

Jul-08

July 3

·          VPN Connectivity to CME Group Certification Environments (CERT and New Release)

·          Request access to the Auto Cert+ Certification Test Suite

July 31

·          Complete Market Data Certification in AutoCert+

Aug-08

August 1

·          Begin parallel production testing of RLC and FIX/FAST

Oct-08

October 17

·          RLC Conversion Completed

October 18 -31

·          $2,000 per week penalty imposed for users taking RLC

Nov-08

November  1-30

·          $4,000 per week penalty imposed for users taking RLC

Dec-08

December 1-30

·          $6,000 per week penalty imposed for  users taking RLC

December 31

·          Elimination of RLC

For VPN Connectivity and access to the Auto Cert+ Certification Test Suite, please contact Market Data Operations at mdo@cmegroup.com.

 

Please contact mdo@cmegroup.com if you have any questions concerning this notice. Thank you